🚧 Behind the K-Rail: Week of Nov. 16, 2026
Another step closer to building the new Mission Boulevard Bridge!
Crews are nearly finished constructing the foundation and support structures for the northern bridge span, including bridge piles, columns and abutments.
🔹 The northern span has 10 columns, arranged in five sets of two.
🔹 The final column concrete pour is planned for early December.
🔹 Once column construction is complete, crews can begin building the temporary support system, known as falsework, for the new bridge deck.
⚠️ As construction continues, please slow down through the project area, watch for crews, and share the road with cyclists.
Follow the project’s progress and sign up for email or text updates at MissionBlvdBridge.com.