🚧 Behind the K-Rail: Week of Nov. 16, 2026 

Another step closer to building the new Mission Boulevard Bridge!  Crews are nearly finished constructing the foundation and support structures for the northern bridge span, including bridge piles, columns and abutments.  🔹 The northern span has 10 columns, arranged in five sets of two.  🔹 The final column concrete pour is planned for early December.  🔹 Once column construction…

Read More

🇺🇸 Thank You, Veterans 🇺🇸

🇺🇸 In observance of Veterans Day, no construction work will take place on Wednesday, Nov. 11, 2026. ⚠️ Traffic control will remain in place along Mission Boulevard in the project area. Please reduce speed, proceed with caution, and follow posted traffic signs when traveling through the project area. Stay informed on upcoming construction activities by signing up for email or text updates on the Mission Blvd. Bridge Project website.

Read More

Behind the K-Rail: Week of Nov. 2, 2026 🚧 

Building from the ground up! Crews are making progress on the foundation and supports for the new northern bridge span.  ⚠️ As construction continues, please slow down through the project area, watch for crews, and share the road with cyclists.  Follow the project’s progress and sign up for email or text updates at MissionBlvdBridge.com. 

Read More

🚧 Project Update: Friday, Oct. 23, 2026 🚧 

Concrete work continues as crews construct piles, columns, and abutments that will support the new northern bridge span. Please reduce speed and use caution when traveling through the construction area. Traffic conditions may change due to weather or field conditions. Stay up to date on project progress and upcoming construction activities at MissionBlvdBridge.com.

Read More

We give a hoot!

🦉✅ Environmental Stewardship Along the Santa Ana River   Earlier in the project, a great horned owl nest was identified near the Mission Boulevard Bridge Project site and protected by the project’s environmental team.   With monitoring and protective measures in place, the nest successfully fledged and the owl family completed its nesting cycle in May 2026 — an…

Read More

As progress continues on the Mission Boulevard Bridge, take a look at a few of the improvements coming to this important connection between Jurupa Valley and Riverside. 

🔹 State-of-the-art bridge meeting current seismic and safety standards  🔹 1,100-foot-long bridge with two traffic lanes in each direction  🔹 Added shoulders and a raised center median to improve safety  🔹 Separated multipurpose trail for pedestrians, equestrians and cyclists  🔹 Connection to the Santa Ana River Trail  The renderings offer a glimpse of what the…

Read More

🚧 September Safety Spotlight: Share the Road  🚧 

As summer winds down, daylight fades, and fall approaches, remember to look out for everyone traveling through the Mission Boulevard Bridge project area.  🔹 Cyclists are permitted to use the full lane when traveling across the bridge  🔹 Reduce speed and give cyclists plenty of space  🔹 Stay alert and follow posted construction signage  🔹 Watch for crews working…

Read More

🚧 Project Update: Friday, September 4, 2026 🚧 

Another step forward for the Mission Boulevard Bridge Project!  ✅ On Wednesday, Sept. 2, crews placed concrete for an abutment and retaining wall, continuing progress on the northern bridge span.  🔹 Looking ahead: Crews will not be working Monday, Sept. 7, in observance of Labor Day. Traffic control will remain in place throughout the holiday, and construction…

Read More

Construction Update: August 14, 2026

OPEN–SANTA ANA RIVER TRAIL  The temporary Santa Ana River Trail closure at Mission Boulevard is complete, and the trail is now open to pedestrians and cyclists. Thank you to trail users and the community for your patience and cooperation while crews completed construction activities adjacent to the trail. ⚠️ Construction continues in the area; please use caution and…

Read More